Robex remains on track for first gold at Kiniero in Q4 CY2025

August 26, 2025

Highlights:

  • Construction at Robex’s Kiniero Gold Project, Guinea, remains on schedule and budget - first gold pour on track for Q4 CY25. Project remains LTI free (lost time injury) with 3,917,695 hours worked since January 2023.
  • Drilling at Sabali pit continued, with 35,518 metres drilled in July and 32,184 samples pending analysis.
  • Process plant and power station concrete is nearing completion.
  • Field erected tankage is 83% completed. Both CIL tank trains completed with intertank launders installed.
  • SMP (Structural, Mechanical & Piping) works progressing well at 22% complete, erected or preassembled.
  • Fuel storage facility tankage erection progressing ahead of schedule.
  • Construction of the tailings storage facility main eastern embankment continues.
  • Mining Services Contractor mobilisation is progressing, with 70% of Tranche 1 equipment delivered to site.
  • Overland piping installation works is progressing ahead of schedule with 8, 42% completed.
  • Electrical works are underway with the team completing cable ladders installation.


Figure 1: Aerial view of the Kiniero site showing process plant and infrastructure (19 August 2025)


Figure 2: View of Milling building showing mill suspended slab completed and SAG Mill Installation (13 August 2025)